What Happened?

If your power project is waiting in line to connect to the electric grid, a Senate bill could move certain fossil fuel plants ahead of it. The GRID Power Act cleared the Senate Energy and Natural Resources Committee without changes Sept. 30, and Sen. Mike Lee (R-UT) formally reported it Nov. 12, according to a Legis1 review of the bill's history. ​

Lawrence Berkeley National Laboratory (LBNL) reported nearly 2,600 gigawatts of generation and storage capacity were awaiting connection at the end of 2023, in Queued Up: 2024 Edition. Here is what the bill would do:

  • Rule rewrite: The Federal Energy Regulatory Commission (FERC), the federal agency that oversees grid connection rules, would have to revise its interconnection rules.
  • Higher spots: Companies that run power lines could propose higher queue positions for what the bill calls dispatchable power projects, including certain fossil fuel plants.
  • 60-day clock: FERC would have 60 days to approve or deny each proposal.

Why Does it Matter to Me?

Developers already in the connection line face the most direct change, because a plant could get a higher spot if FERC approves a proposal for it.

FERC's earlier rule set up a "first-ready, first-served" cluster-study process to reduce delays, according to the agency. The bill would add a way for certain projects to get higher priority than that process gives them.

Both Sides, Now

Supporters say the change would improve grid reliability and make sure there is enough electricity generation. Critics say it could let natural gas plants bypass renewable energy projects that are already waiting.

Sen. John Hoeven (R-ND), who introduced the bill Feb. 6, 2025, said after the committee vote that it would help eliminate delays for dispatchable projects and strengthen reliability. Sen. Todd Young (R-IN), an original cosponsor, wrote in a Sept. 26, 2025, post on X that he introduced it "to promote energy independence and baseload power."

Sen. Martin Heinrich (D-NM), the committee's ranking member, said in an Oct. 6 statement that the bill would "codify 'queue jumping'" for natural gas plants.

A similar fight has played out elsewhere. In March 2025, the Sierra Club, Appalachian Voices and other groups asked FERC to rehear its approval of a separate plan by PJM, a grid operator, objecting that large gas plants could jump ahead of renewable projects that had waited for years, pv magazine USA reported. All four Senate cosponsors are Republicans. The House passed its own version of the GRID Power Act Sept. 18, 2025, by 216-206, with 211 Republicans and five Democrats in favor.

What Happens Next?

The full Senate would have to pass the bill, and the House and Senate would have to agree on one version before it could go to the president for a signature. The bill now awaits action by the full Senate.

---